Falcon Equipment Procurement: 7 Questions, Answered by a Cost Controller

Posted on Monday 3rd of August 2026 by Soren Valgaard

Over the last seven years, a few procurement questions keep coming back — from our own team, from vendors, from other buyers picking my brain. I'm the procurement manager at a 240-person mining operation. I manage roughly $1.4 million a year in equipment and parts spend, and I've documented every order in our cost tracking system.

Here's what people ask me most:

  • Is Falcon equipment worth the higher price?
  • How should I read a Falcon 7X pricing quote?
  • What hidden costs catch buyers off guard?
  • Should we buy refurbished or new?
  • How do I budget for maintenance and parts?
  • What's different about brownfield sites?
  • When should we upgrade instead of repair?

1. Is Falcon equipment worth the higher price?

The short answer: usually, yes. But I'd rather show you my math than ask you to trust me.

In 2023 I audited our spending across nine vendors. Two of them made the same class of component — a budget brand and Falcon. The budget brand quoted 25% less upfront. But when I pulled the maintenance logs, those cheaper units needed service twice as often. The budget brand was fine for light duty cycles. For continuous operation, it just didn't hold up. In one year, the "savings" turned into $45,000 of extra downtime and labor.

Here's the thing: price is what you pay. Cost is what you live with.

2. How should I interpret Falcon 7X pricing when comparing quotes?

Pricing sheets rarely tell the whole story. When I get a quote for the Falcon 7X line — yes, the number is higher than some competitors — I ask three questions right away:

  • What's not included? Installation, commissioning, operator training?
  • What happens when it breaks? Response time, parts availability, loaner units?
  • What does the warranty actually cover? Wear items, labor, travel time?

I learned this the hard way. In Q2 2024 we switched vendors for a drilling support system. The quote was $22,000 cheaper. But the extras — commissioning, tooling, a monthly software fee nobody had mentioned — added up to $27,500. The "cheaper" option cost us $5,500 more.

I still kick myself for not asking "what's NOT included" earlier. The seller didn't hide anything. I just didn't ask.

3. What hidden costs should I plan for when buying equipment?

The most frustrating part of equipment procurement: hidden costs don't show up on the invoice. They show up months later in the project folder, when nobody remembers who approved them.

The ones that show up in my cost tracking system most often:

  • Freight and site access — if the road needs upgrading to move the equipment, that's on you.
  • Storage — equipment that arrives early still costs money to sit somewhere.
  • Training — if nobody on site can operate the new system safely, "free installation" doesn't help.
  • Commissioning spares — the parts you burn during setup that the warranty doesn't cover.

One vendor's "free setup" ended up costing us $450 in extra fees — $150 for a "site visit" that was actually a phone call, and $300 for expedited paperwork. That's when I started asking for itemized quotes.

My rule now: take the quoted price, add 15–20%, and if the project still makes sense, proceed. Period.

4. Refurbished or new Falcon equipment?

A genuine dilemma. The upside was $80,000 in savings on a refurbished processing unit. The risk: unknown maintenance history. I kept asking myself — is $80,000 worth potentially losing two weeks of production?

What swayed me: the unit came with a 24-month warranty, and the seller documented every replaced component. We bought it. Three years later it's still running.

But I've seen the opposite too. A "like new" motor for another project had internals that looked like they'd been submerged. We paid $1,200 and got $1,200 of scrap.

So my rule: refurbished is fine when the history is documented and the warranty is real. Otherwise, buy new.

5. How do I budget for maintenance and parts?

Most buyers budget for the purchase price, then get surprised by the maintenance.

I track total cost of ownership in a spreadsheet. Every asset gets a maintenance estimate per year, expected repair frequency, parts consumption history — updated after every job — and a downtime cost per hour.

After tracking 2,100+ orders over six years, I found that 30% of our budget overruns came from one cause: emergency parts orders with premium shipping. We implemented a minimum-stock policy for critical items and cut overruns by 40%.

Steven, our maintenance lead, jokes that my spreadsheet is the most critical piece of equipment we own. He's not wrong.

6. What's different about buying for brownfield sites?

Brownfield projects are a different animal. You're not building on an empty plot — you're integrating new equipment into a site that's still running.

Things that caught us off guard at first:

  • Existing foundations may not match the new equipment footprint.
  • Power and control systems may not support modern gear.
  • Installation windows are shorter because production continues.

My honest advice: pay for a site survey before you request quotes. An $8,000 survey saved us $112,000 in rework on one project. Best money we spent that year.

7. When should we upgrade instead of repair?

The answer depends on one number: cost per hour of downtime.

In late 2024, a critical compressor started failing. Repair quote: $30,000. Upgrade: $95,000. On paper, repair wins. But our downtime cost for that machine is $2,800 per hour. The repair had a 14-day lead time and no guarantee it would last 12 months. The upgrade had a shorter lead time and a 3-year warranty.

The math wasn't close. We upgraded.

I've made the wrong call too. The worst budgeting mistake I've made was deferring a $20,000 replacement to save money. The old unit failed mid-month. Emergency repair plus lost production came to $40,000.

Nobody gets every equipment decision right. The point is to get the cost math clear before you decide. As of January 2025, these are the questions sitting on my desk — and if you're evaluating Falcon equipment, they're probably on yours too. Ask what's NOT included. Track the full cost. Do the math.

Soren Valgaard

Soren Valgaard covers surface and underground drill rigs, rotary drills, core drills, rock drills, DTH hammers, drill bits, and rock-reinforcement equipment. His evaluations reference ISO 18758-1 while comparing hole diameter, drilling depth, penetration rate, feed force, compressor demand, rod handling, fuel use, and rig stability. He helps mine engineers and equipment buyers match drilling systems to geology, bench design, production targets, operator safety, mobility, and maintenance conditions.